Mature Fields
Solve the issues causing delays and decreasing production in the heavy oil field
Boscán Field, Zulia, Western Venezuela
Solve two main issues that decreased production and caused delays in heavy oil wells:
WellSET® module and laboratory testing to optimize particle size distribution of bridging agents in BARADRIL-N® drill-in fluid
The Boscán field, located in the state of Zulia in western Venezuela, is a large field that produces crude oil with 9.5 to 12 API gravity and a viscosity of 130–500 cp, depending on temperature related to reservoir depth. The 175°F (79.4°C) reservoir consists of basal Oligocene sandstones above and upper Eocene sandstones below. Matching a filter cake breaker to the physical characteristics of this crude called for a special formulation designed to restore permeability in the pay zone while mitigating asphaltene precipitation and preventing emulsion formation. The selected breaker would need to perform well with a wide range of completion types.
The team used the WellSET® module, along with rigorous laboratory testing, to optimize the particle size distribution of bridging agents in the BARADRIL-N® drill-in fluid. This helped prevent fine solids invasion in the 8-1/2-inch reservoir interval.
After reaching the reservoir total depth (TD), the Boscán wells were completed with a variety of completion systems, including gravel-packed slotted liners and standalone screens. Each reservoir was treated with a customized N-FLOW™ 325 delayed-reaction filter cake breaker that could be pumped and distributed evenly throughout the pay zone before converting to acid. The ability to completely remove the filter cake is ultimately dependent on the thickness of filter cake and the surface area/volume of filter cake breaker ratio. The Boscán field is drilled with an overbalance of 1,000+ psi. The delayed-acid generator reacts with water to slowly release an organic acid downhole. The acid dissolves calcium carbonate and polysaccharides in the filter cake, thereby removing mud damage in the downhole interval.
Drilling fluid filtrate, crude oil and brine can all create emulsions when they mix, and this had been a problem in this field. The customized N-FLOW formulation was designed to minimize risk of emulsion blocking. It was mixed with an optimized concentration of NO BLOK® C non-emulsifier, which had been tested extensively in the lab under simulated field conditions.
Increase in production
With the use of the N-FLOW system, the reported production rates showed a 30 percent increase throughout the entire field.
The N-FLOW in-situ acid treatment has proven to be non-emulsifying, thermally stable, water-wetting, and devoid of mineral acid. It reliably mitigates acidic sludges and hydrocarbon precipitants to provide uniform filter-cake removal within the pay zone.
Using the N-FLOW breaker system also saved rig time. Because of its delayed reaction and safe handling at the surface, the N-FLOW breaker could be mixed and pumped with the drilling rig, eliminating the need to move in a workover rig for this purpose and avoiding health, safety, and environmental (HSE) incidents.